Single storey extension – Progress

Final Building control inspection done, everything ok and permission to crack on getting the building fully watertight.

Once the building was tiled we installed the new upvc windows and also the Velux roof window.

The roof tiles we used are a modern concrete alternative and look and feel like slate but without the weight.

Electrics were installed and all the pipe work for water supply and central heating laid to the new extension.

The inside walls were then boarded and plastered.

We installed the fascia and soffit boards, gutter and installed the drains for the drainpipe and kitchen sink.